Container City™ was engaged to build a new head office for Bristol & Avon Group at its site in Hallen, near Avonmouth.
After careful preparation, the prefabricated structure was installed over five days in April 2016.
A Chinese box puzzle of interrelated modules, the building presents an arresting facade with colour used to good effect to emphasise the B&A brand.
Key Facts
Use: Offices
Client: Bristol & Avon Group
Design/ Build: Container City™/ Mackenzie Wheeler
Engineer: Furness Partnership
Installation time: 5 days
Total space: 675m2